MIVARE LABS SPACE RENOVATION AND INTERIOR FIT-OUT MANAGEMENT SYSTEM
Schedule. Mivare Space Help Centre
AREA 01 · PROJECTS · TOPIC 04

Schedule

The schedule answers one question: does the project plan add up. The chart shows what stands when, and the band above it shows what clashes.

IN THE APP
Modules › Projects › Schedule
WINDOW
4, 8, 12 or 26 weeks
CONFLICTS
Four kinds
CONNECTIONS
4 modules

01What it is

The schedule draws the tasks of the chosen project on a chart: one column is one day, and a bar runs from the start to the end of the task. The window begins on Monday of the current week.

A conflict always points at two entered rows that clash: a broken dependency, one person in two places, a team assigned elsewhere or a task ending after the job deadline.

A milestone is a date the rest of the plan depends on, for example “installations run”. It has no duration and no assignee.

CHART
A bar per task, a diamond per milestone.
CONFLICTS
Dependency, same person, team elsewhere, past the deadline.
UNDATED
Tasks without a date sit under the chart.

02What it is for

A plan in weeks

A window of 4 to 26 weeks for one project.

A conflict before it happens

One person on two tasks at once shows up straight away.

The team where it is needed

A conflict when the team works on another project that day.

The job deadline

A task ending after the job deadline is flagged.

03Main options

The schedule screen is the chart, the conflict band and the list of milestones.

What stands when

Tiles: tasks in window, conflicts, milestones, undated.

  • Choice of project and window: 4, 8, 12 or 26 weeks
  • A bar from start to end of a task, a diamond on the milestone day
  • Undated tasks under the chart
Chart

04Tasks step by step

  1. STEP 1Open Modules › Projects › Schedule.
  2. STEP 2Choose the project and the window, for example 8 weeks.
  3. STEP 3Read the conflict band above the chart. Each row says which task clashes and why.
  4. STEP 4Correct the date or the assignee in the task and return to the schedule.

05Actions

The most common tasks around the schedule.

New milestone

A date the rest depends on.

Tasks

The task register and form.

Week window

4, 8, 12 or 26 weeks.

06What it connects to

Choose a module to see where the schedule takes its data from.

PROJECTS

Tasks

The chart and its conflicts are built from tasks.

Go to the topicTasks