MIVARE LABS SPACE RENOVATION AND INTERIOR FIT-OUT MANAGEMENT SYSTEM
Issues. Mivare Space Help Centre
AREA 04 · TEAM ON SITE · TOPIC 05

Issues

A register of things that need a decision or a fix: a defect, a hazard, blocked access, missing material. A task says what we do; an issue says what is wrong, where, how urgent it is and whether it moves the project deadline.

IN THE APP
Modules › Team on site › Issues
WORKFLOW
Open to closed
RESOLUTION
Always described
CONNECTIONS
6 modules

01What it is

An issue belongs to a project and can point to a unit and a job. It has a type, a priority, a schedule impact, an assignee and a due date.

The workflow is fixed: open, in progress, resolved, closed. Resolving requires a description of what was done. Reopening clears the repair date and description; the old text stays in the history.

A resolved issue cannot be deleted, because six months later it is the evidence that the work was done.

TYPES
Safety incident, defect, hazard, obstruction, missing material, other.
SCHEDULE IMPACT
No impact, risk of delay or delay.
WHERE
Project, unit and job in one path.

02What it is for

Nothing left hanging

The Overdue tile and the overdue issue notification.

Protect the deadline

A separate filter for issues that affect the project deadline.

Know who worked there

The record shows assigned teams and confirmed attendance from before the issue.

Arguments for a dispute

Customer acceptances and earlier repairs in the same unit.

03Main options

Issues is a list with filters, the issue form and a record with tabs that answer the questions asked in a dispute.

What is wrong and how urgent it is

Tiles: Unfinished, Overdue, Critical and Move the deadline.

  • Filters: project, status, priority and due date
  • Due: only unfinished, overdue, within 7 days, with schedule impact, no due date
  • Search by title, description and repair description
Issue list

04Tasks step by step

  1. STEP 1Open Modules › Team on site › Issues and choose New issue.
  2. STEP 2Enter a title, for example Crack in the skim coat, living room, window wall.
  3. STEP 3Pick the project, unit and job, set the type Defect, the priority and the due date.
  4. STEP 4Save. The issue is open.

05Actions

The most common tasks around issues.

New issue

A defect, hazard or shortage.

Start working

The issue moves to in progress.

Resolve issue

With a description of what was done.

Close issue

Once the fix is checked.

Create task

A remedial task with a job and date.

Reopen issue

When the problem comes back.

06What it connects to

Choose a module to see where the issue record takes its data from.

PROJECTS

Tasks

A remedial task is created from the issue record and blocks deleting the issue.

Go to the topicTasks